Requesting Entity: RPB Commercials

Issues Concern: Completed Similar Project

Details

Whether or not the requirement that the value of the completed project similar to the contract to be bid must be at least fifty percent (50%) of the approved budget for the latter applies only to contracts involving infrastructure projects and not to contracts involving the supply and delivery of goods and equipment.

It is clear from [Sections 23.11.1 (2) and 23.11.2 of the IRR-A] that the requirement setting the value of the prospective bidder’s single completed contract which is similar to the contract be bid to be at least fifty percent (50%) of the approved budget for the contract to be bid applies to both goods and infrastructure projects.