NPM No. 116-2013

Requesting Entity: Himex Corporation (Himex) Issues Concern: Disapproval of the Recommendation of the Bids and Awards Committee (BAC); Protest Mechanism Details Remedies available to a bidder after the Head of the Procuring Entity (HOPE) disapproved the BAC resolution recommending the contact award in its favor. The notice of disapproval by the HOPE of the recommendation continue reading : NPM No. 116-2013

NPM No. 117-2013

Requesting Entity: Government Arsenal (GA) Department of National Defense Issues Concern: Composition of Post-qualification Team Details Clarification on the composition of a post-qualification team, and whether the same should be headed by a Bids and Awards Committee (BAC) member. Neither Republic Act No. (RA) RA 9184 nor its revised Implementing Rules and Regulations (IRR) provides continue reading : NPM No. 117-2013

NPM No. 119-2013

Requesting Entity: Bases Conversion and Development Authority (BCDA) Issues Concern: Additional Deliverables in an Existing Design Consultancy Contract Details Whether BCDA could revise and include additional deliverables to its existing design consultancy contract. BCDA may revise the existing design contract to include additional deliverables, provided, however, that such revision will entail no additional payment or continue reading : NPM No. 119-2013

NPM No. 118-2013

Requesting Entity: Edro Construction (Edro) Issues Concern: Statement of On-going and Completed Contracts Exception to the Single Largest Completed Contract (SLCC) Requirement; Mayor’s Permit from the Local Government Unit (LGU)-Procuring Entity; Review of Bids and Awards Committee (BAC) Resolution Details 1.Request to review the Bids and Awards Committee (BAC) resolution issued by the Municipality of continue reading : NPM No. 118-2013

NPM No. 121-2013

Requesting Entity: Manila International Airport Authority (MIAA) Issues Concern: Submission of Request for Reconsideration During Bid Evaluation; Effect of Non-Posting of the Bid Bulletin in the Philippine Government Electronic Procurement System (PhilGEPS) Details Whether the MIAA Board should grant a request for reconsideration on its decision approving the recommendation of the MIAA Bids and Awards continue reading : NPM No. 121-2013

NPM No. 120-2013

Requesting Entity: Administrative & Financial Management Service National Anti-Poverty Commission (NAPC) Issues Concern: Posting of Performance Security by Non-Governmental Organizations (NGOs) Details Whether NGOs selected to perform contracts acquired through Negotiated Procurement (NGO Participation) under Section 53.11 of the revised Implementing Rules and Regulations (IRR) of Republic Act No. (RA) 9184 are required to post continue reading : NPM No. 120-2013

NPM No. 122-2013

Requesting Entity: Alenia Aermacchi Issues Concern: Extension of Bid Closing Time; Late Issuance of Supplemental/Bid Bulletin; Declaration of Failure of Bidding Details Extension of the Bid Closing Time If the procuring entity intends to postpone or reschedule the deadline for the submission and receipt of bids, it may do so by issuing a Supplemental/Bid Bulletin continue reading : NPM No. 122-2013

NPM No. 110-2013

Requesting Entity: DBP Leasing Corporation (DLC) Issues Concern: Exemption from Disqualification as Servicing Agency under Negotiated Procurement (Agency-to-Agency) Details Whether DLC is exempted from the rule disqualifying non-chartered Government Owned and/or Controlled Corporations (GOCCs) from being engaged as Servicing Agency through Negotiated Procurement (Agency-to-Agency) under Section 53.5 of the revised Implementing Rules and Regulations (IRR) continue reading : NPM No. 110-2013

NPM No. 109-2013

Requesting Entity: Subic Bay Metropolitan Authority (SBMA) Issues Concern: Negotiated Procurement (Two Failed Biddings) Details Whether SBMA may consider the proposals of suppliers who participated in the Negotiated Procurement (Two Failed Biddings) under Section 53.1 of the revised Implementing Rules and Regulations (IRR) of Republic Act No. (RA) 9184 for the procurement of One (1) continue reading : NPM No. 109-2013

NPM No. 111-2013

Requesting Entity: Advance Solutions, Inc. Issues Concern: Statement of On-going and Completed Contracts Details 1.Whether projects may be considered as “ongoing” if it has been awarded to the bidder through the issuance of the Notice of Award (NOA) by the Head of the Procuring Entity (HOPE), but no contract has been signed yet. Projects where continue reading : NPM No. 111-2013