Home
About Us
GPPB
GPPB-TSO
Issuances
Resolutions
Circulars
Guidelines
Opinions
› Policy
› Non-Policy
Downloadables
Listings
Blacklisted Suppliers
Suspended Suppliers
Blacklisted Constructors
Suspended Constructors
CPES Reports
Other Listings
Related Laws
Statutes
› Commonwealth Acts
› Executive Orders
› Letter of Instructions
› Presidential Decrees
› Republic Acts
Executive Issuances
› Administrative Order
› Executive Orders
› Memorandum Circulars
› Memorandum Orders
Other Issuances
Bulletin Board
Updates
Training Events
Reporting Compliance
Links
Government Agencies
GPPB Online Forum
Other Links
Contact Us
Guestbook
Email Us
NPM No.
NPM 057-2009
Date
10/16/2009
Requesting Entity
Allied Trade Resources
Subject
Submitted vs. Calculated Bid Prices
Issues/Concern
Whether the Contract Price Award should be based on the Calculated Bid Price, or the Submitted Bid Price of the bidder.
A reading of [Sec. 37.1 of IRR-A], taken together with Sec. 37 of RA 9184, leads us to the conclusion that the contract should be awarded to the bidder with the Lowest Calculated Responsive Bid at the amount determined by the BAC to e whichever is lower between the actual submitted bid price, and the evaluated, calculated bid price. Hence, in case of discrepancy between the two amounts, the lower shall prevail.